At the beginning of April 2011 MTX were awarded the contract to supply and install a temporary ultra clean operating theatre suite with two-bed recovery bay at Glan Clwyd Hospital for Betsi Cadwaladr University Health Board in North Wales.
The new modular installation, which is due to be completed in a programme of just 8 weeks, is being installed to allow the hospital to decant their existing 5 theatres. As part of the installation project MTX have also been contracted to design and install a 3 bay link way to give access to the existing hospital and provide additional storage space.