Testimonials

In partnership with J&JMS, MTX have delivered an exceptional building which provides GSTT with additional surgical and recovery capacity. Despite the constant challenges associated with delivering a build project within

Adam Davies
Operations Manager for Johnson & Johnson
July 1, 2019

“MTX were appointed in early 2018 to deliver a modular building consisting of two operating theatres, Endoscopy procedure room and ancillary accommodation, including a 7 space recovery unit. The building

Graham Alexander
Project Director for Betsi Cadwaladwr University Healthboard
April 25, 2019

“MTX have delivered a building fit for purpose, on time, to budget and to the quality we would expect. MTX have been great partners throughout the whole process and very

John Fulcher
Head of Capital Projects for Colchester Hospital University NHS Foundation Trust
December 18, 2017

“It has felt like a strong partnership throughout. The company has been very honest, straightforward and transparent, including on cost. The nice thing about working in partnership is that you

Julie Richards
Associate Director of Estates
December 5, 2017

“MTX were extremely proactive, accommodating and understanding of our needs. The project included groundworks that revolved around archaeology and the contractor acted in a compliant manner, engaging with all stakeholders

Graham Vaughan
Capital Programme Manager for Wye Valley NHS Trust
February 28, 2017

“MTX have recently completed a state-of-the-art PET / MR Scanner Suite on a design and build contract for their client; Engie Buildings Limited at the Central Manchester University Hospital Trust

Andrew Hopwood MCIOB
Project Manager – Consulting, Lendlease
December 1, 2016

“The scheme was delivered both on time and within budget with thoroughly professional managers and site management. The Project Team worked with the Trust throughout the design and construction period.

Patsy Tobin
Lead Commissioning & Clinical Planning Manager
June 28, 2016

“MTX delivered a great building and enabled the Trust to make use of 63 beds within 11 months. The facility is sandwiched between a 24 hour A&E department and theatre

Muhammad Syed
Head of Capital Projects for London North West Healthcare NHS Trust
April 19, 2016

“I found MTX to be a complete pleasure to work with throughout all stages of procurement, design development, and off site and on site construction. The scheme was handed over

Colin Plant
Divisional Director – Estates and Facilities, Walsall Healthcare NHS Trust
July 27, 2015

“MTX are an excellent company to work with. The PROJECT TEAM worked with the Trust throughout the design and construction period. Every effort was made to minimise disruption on the

Malcolm Courtney
May 7, 2015

“Our scheme consisted of a circa 1500m2 development over 3 floors. During our interaction with MTX we found you to be thorough, knowledgeable and willing to work with the estates

Nigel Bond
May 7, 2014

“The Trust is exceedingly pleased with the building as a whole. This expansion was an essential requirement to achieve performance standards for the A&E department specifically and the hospital as

David Stonehouse
April 16, 2014

“We have successfully worked with MTX on several capital projects over a number of years and found them to offer an excellent service. On this occasion we set an almost

Paul Holt
Director of Estates, Stockport NHS Foundation Trust
March 4, 2014

“Having worked with MTX upon this particularly complex and challenging modular building from scheme conception through to completion, all credit must be awarded to MTX and their award winning site

Michael Smethurst
Project Planner, Laing O'Rourke
February 6, 2013

“The extent, scale and scope of the (90-phase) project is clearly substantial. In this first phase, MTX must take great credit for the standard of its work, for its excellent

Colin Chong
Project Leader, Laing O'Rourke
October 12, 2012

“Given the technical and challenging nature of the lift, and the critical environment that surrounded the site, to complete a milestone event without any major issues or impact on external

Michael Smethurst
Project Planner, Laing O'Rourke
October 10, 2012

“The MTX team communicated well with myself and my colleague and were always approachable for any queries we had. They fully appreciated the need to restrict disruption to the existing

Marion Washer
New Cross’s Directorate Manager
October 10, 2012

“We are sure that patients will be impressed when they see the theatres.”

Elaine Ryan
Divisional Head, Leicester General Hospital
September 21, 2012

“Staff using the new theatres have been very positive about them.”

Mr Andrew Brown
Consultant Orthopaedic Surgeon, Leicester General Hopsital
September 21, 2012

“It was MTX’s commitment and willingness to supply what we (the Trust) wanted that set them apart from other modular building specialists. Their flexibility and commitment to meet our needs

Paul Holt
Estates Director, Stockport NHS Foundation Trust
April 16, 2012

“The project had to be completed to an extremely tight schedule, but despite the considerable time pressures, and the structural and other construction challenges MTX faced, they delivered the new

Anthony Downey
Head of Estates and Capital Projects, Heatherwood and Wexham Park Hospitals NHS Foundation Trust
January 10, 2012

“When I saw the finished facility I thought it was absolutely stunning, especially given the very limited space MTX had to work with. The company also extremely skilfully managed the

Mandy Claridge
General Manager, Surgical Services at Heatherwood and Wexham Park Hospitals NHS Foundation Trust
January 10, 2012

“We would like to bring to your attention our appreciation of the hard work and support of your (service) team here at Paddock Wood. Despite the weather conditions that have

Tim Espley
Operations Director, M&W Mack Limited
July 1, 2010

“The project has received a subjective thumbs up… the exterior appearance is attractive; the wood panelling looks nicely under-stated and gives a very “natural” feel to the building.”

Tristan Shanahan
Facilities Manager Stanmore College
September 21, 2009

“There is no doubt that many architects have been somewhat dismissive about modular buildings in the past, tending to view them exclusively as temporary facilities built down to a cost

Narciso Simioni
Taylor Young (Architects)
April 17, 2009